- Make ready 5G greenfield rooftop structure including slab scan, fire proofing, core hole for feeder cable;
- Installation of mains power, generator inlet and air conditioning;
- Completed make ready work in the fit-out room (relocated water, fire system and installed feeder window);
- Installed cable tray including provision of materials;
- Completed installation of new steelwork for three sectors;
- Installed equipment onto new mounts for three sectors including 9 antennas, RRU’s, combiners and al required plumbing;
- Design, supply and installation of PVC shroud cover;
- Installed new antennas (lens, panel and parabolic) and RRU’s, swapped, moved and upgraded existing antennas and completed all associated plumbing;
- Installed and cabled all new internal equipment for all wireless technologies and integrated and commissioned the service.
Client Outcomes
- Complex rooftop greenfield project completed within budget and schedule demonstrating CITA’s range of capabilities;
- Successfully planned and implemented the high risk site safety requirements involving night work, scaffolding, crane and scissor lifts, working at heights, traffic and pedestrian management;
- Successfully managed all stakeholders to achieve clients desired outcomes.
- Decommission existing RBS6120 and B174 cabinets and cable ladder between cabinets;
- Decommission existing PDB and h-frame support and relocated all the equipment and accessories to shelter meter box;
- Installed concrete shelter foundation and new shelter, installed new electrical pit and connected power;
- Decommissioned and relocated existing antennas per design specifications;
- Installed new antennas (lens, panel and parabolic) and RRU’s, swapped, moved and upgraded existing antennas and completed all associated plumbing;
- Installed and cabled all new internal equipment and integrated and commissioned the service for the NBN.
Client Outcomes
- Complex site works completed on time, within budget and on schedule;
- Identification and reuse of existing coax and fibre cable to minimise cost for client;
- Removal and disposal of decommissioned equipment in accordance with environmental and local council requirements.
- Greenfield design to construct a 40-metre free standing tower with communications hut.
- Included working with various government departments to ensure all requirements were met as well as
- Safe implementation in a public access lookout location.
- Demonstrated our end-to-end capability including our antenna system techncial capabilities.
Client Outcomes
- Foundation and earthing system complaint to NSW Telco Authority requirements;
- Installed tower, hut, cabling and antenna equipment;
- Commissioned all feeders;
- Our effective stakeholder management to achieve the desired project outcomes.
- Delivery of existing monopole foundation upgrade.
- Installation of steel jacket to strengthen the pole.
- Installation of new headframe for the OPTUS and Vodafone network with antennas, hybrid cable, RRU, TMA.
- Building of the Comms Room, AC Power to Comms Room.
- Installation of A/C unit, installation of all internal radio and communication equipment.
- Also include Testing, Commissioning and Integration to OPTUS and Vodafone network with Handover Pack documents.
Client Outcomes
- Delivered the site for the on-air target date;
- Kept existing Telstra services live throughout the construction period;
- Kept client up to date with design changes and obtained speedy approvals to keep the completion milestones intact;
- Kept Building Manager engaged to minimize disruptions to his multi-tenant daily operation.
- Removal of existing electrical meter board from Vodafone fire damaged shelter and reconnected Optus power.
- Removal and disposal of Vodafone shelter, preserving existing incoming coax and fibre cable.
- Re-established foundation for new shelter.
- Installed the new shelter and connected the power.
- Installed and cabled all new internal equipment and integrate and commission the Vodafone service.
Client Outcomes
- Relocate and reconnect Optus power to minimise generator usage;
- Worked with the client to locate spare equipment and restore live service on air with 5 weeks;
- Identify and reuse of existing coax and fibre cable to minimise cost for client;
- Remove and disposal of fire damage equipment as per Site Environmental Management Plan and local council requirements.
- Decommissioning and removal of existing 30m tower and foundation.
- Removal of trees and site levelling.
- Construction of new 45m tower structure including foundation, antenna, coax cables, TMA, combiners and radio equipment.
- Testing, Commissioning and Integration to Telstra network with Handover Pack documents.
Client Outcomes
- Developed a MOP to safely dismantle the old tower.
- Site on air date achieved one week earlier than the planned date.
- Our detailed methodology, ensured no issues on any of the incoming or outgoing underground services around the existing Telstra Exchange Building.